conductor(plan): Mark Phase 9 complete in chronology_20260619/state.toml

This commit is contained in:
2026-06-20 17:59:52 -04:00
parent b4f313d21a
commit 7d13bb32e8
@@ -23,7 +23,7 @@ phase_5 = { status = "completed", checkpointsha = "07afef2", name = "Write docs/
phase_6 = { status = "pending", checkpointsha = "", name = "User review of draft" }
phase_7 = { status = "completed", checkpointsha = "8cd9285", name = "Final commit (rename draft to canonical)" }
phase_8 = { status = "completed", checkpointsha = "271e689", name = "Per-row cross-check (FR6 hard gate; bulk verification done; manual summary-adequacy check deferred to followup)" }
phase_9 = { status = "pending", checkpointsha = "", name = "Completeness check (FR6 hard gate; folder set vs row set)" }
phase_9 = { status = "completed", checkpointsha = "b4f313d", name = "Completeness check (FR6 hard gate; folder set vs row set)" }
phase_10 = { status = "pending", checkpointsha = "", name = "User sign-off (FR6 hard gate; user is the quality gate)" }