conductor(plan): Mark Phase 3 simulation tests complete

This commit is contained in:
2026-05-10 15:46:59 -04:00
parent fa0a500a38
commit 760054bb4d
@@ -13,9 +13,9 @@
- [ ] Task: Conductor - User Manual Verification 'Phase 2' (Protocol in workflow.md)
## Phase 3: Integration & GUI Verification
- [ ] Task: Write simulation tests for Batch Operations (Shift-Click selection and Action Bar execution).
- [ ] Task: Write simulation tests for the Interactive AST Inspector modal.
- [ ] Task: Write simulation tests for the Slice Editor (adding/removing slices).
- [x] Task: Write simulation tests for Batch Operations (Shift-Click selection and Action Bar execution). (fa0a500a)
- [x] Task: Write simulation tests for the Interactive AST Inspector modal. (fa0a500a)
- [x] Task: Write simulation tests for the Slice Editor (adding/removing slices). (fa0a500a)
- [ ] Task: Conductor - User Manual Verification 'Phase 3' (Protocol in workflow.md)
## Phase 4: Audit & Documentation Sync