Implementation Plan: Track Progress Visualization (track_progress_viz_20260306)
Phase 1: Progress Calculation
- Task: Initialize MMA Environment
- Task: Implement progress calculation
- WHERE: src/gui_2.py or app_controller
- WHAT: Calculate % from ticket states
- HOW: Count completed vs total
Phase 2: Visualization
- Task: Render progress bar
- WHERE: src/gui_2.py
- WHAT: Visual progress bar
- HOW: imgui.progress_bar
- Task: Render percentage text
- WHERE: src/gui_2.py
- WHAT: Numeric % display
- HOW: imgui.text
Phase 3: Additional Features
- Task: Implement ticket counts
- WHERE: src/gui_2.py
- WHAT: Completed/remaining counts
- HOW: Text display
- Task: Implement ETA
- WHERE: src/gui_2.py
- WHAT: Time estimate
- HOW: Average time per ticket
Phase 4: Verification
- Task: Test progress display
- Task: Conductor - Phase Verification