The track had 3 categories of deferred work. Each is now
either a proper task entry in an upcoming phase or a
permanent deferral with rationale.
Resolution:
1. Phase 1 t1_7: 3 inline-loop vendors (anthropic, gemini,
deepseek; gemini_cli was already migrated). Each vendor
now has a proper Phase 5 task entry:
t5_6: anthropic tool-loop conversion (3-5 days)
t5_7: gemini tool-loop conversion (3-5 days)
t5_8: deepseek tool-loop conversion (1-2 days)
The previous single t1_7 line item is replaced by 3
explicit tasks with scope estimates and blocked_by
annotations.
2. Phase 4 t4_3: Meta Llama API. PERMANENT DEFERRED to
Phase 6 t6_1. Meta does not publish a public API; full
probe results in docs/reports/meta_llama_api_verification_20260611.md.
3. Phase 4 t4_7: UI adaptations for new v2 fields.
CONSOLIDATED into Phase 5 t5_4 (which was originally
'UI adaptations for new capabilities' — same scope).
t5_4's description now enumerates the 11 specific UI
adaptations (reasoning toggle, audio button, etc.).
t4_7 is cancelled to avoid duplicate task entries.
Phase 5 expanded scope: 8 tasks total (was 5). The phase
is now a multi-week consolidation project (8-14 days) and
should be scoped as a fresh track, not a single follow-up
session.
Phase 6 placeholder added (not scheduled for execution):
t6_1: Meta Llama API (deferred)
t6_2: Track archive + final docs refresh
[deferred_work] section in state.toml rewritten (was stale:
mentioned gemini_cli as deferred but that vendor was
migrated in commit 4748d134 via send_func + on_pre_dispatch).
Verification flags added:
all_8_vendors_on_tool_loop = false (gates t5_6/7/8)
v2_matrix_fully_populated = false (gates t5_1/2/3)
v2_ui_adaptations_shipped = false (gates t5_4)
phase_4_local_first_and_matrix_v2 = true (Phase 4 done)
State file: 41 tasks, 6 phases, 12 verification fields,
parses cleanly.
Report: docs/reports/qwen_llama_grok_followup_deferred_work_20260611.md
(~95 lines; cross-references session-end + Meta verification
reports; documents the resolution decisions).