ae5dd328e1
|
conductor(plan): Add refinement tasks from user feedback
|
2026-02-23 18:54:43 -05:00 |
|
|
|
b3cf58adb4
|
conductor(plan): Mark phase 'Phase 3: Visual and Tactile Enhancements' as complete
|
2026-02-23 18:48:11 -05:00 |
|
|
|
e3767d2994
|
conductor(plan): Mark Phase 3 tasks as complete
|
2026-02-23 18:47:22 -05:00 |
|
|
|
975fcde9bd
|
conductor(plan): Mark phase 'Phase 2: Layout Reorganization' as complete
|
2026-02-23 18:45:46 -05:00 |
|
|
|
72c898e8c2
|
conductor(plan): Mark Phase 2 tasks as complete
|
2026-02-23 18:44:26 -05:00 |
|
|
|
b1687f4a6b
|
conductor(plan): Mark phase 'Phase 1: Audit and Structural Design' as complete
|
2026-02-23 18:40:00 -05:00 |
|
|
|
0e06956d63
|
conductor(plan): Mark review task as complete
|
2026-02-23 18:39:13 -05:00 |
|
|
|
a359f19cdc
|
chore(conductor): Add new track 'Review GUI design and UX refinement'
|
2026-02-23 16:59:59 -05:00 |
|